U.S. Plans Largest Nuclear Power Program Since the 1970s

read original related products more articles

The United States aims to embark on its most active new nuclear construction program since the 1970s. In its most high-dollar nuclear deal yet, the Trump administration in October launched a partnership to build at least $80 billion worth of new, large-scale nuclear reactors, and chose Westinghouse Electric Company and its co-owners, Brookfield Asset Management and Cameco, for the job.

The money will support the construction of AP1000s, a type of pressurized water reactor developed by Westinghouse that can generate about 1,110 megawatts of electric power. These are the same reactors as units 3 and 4 at the Vogtle nuclear plant in Georgia, which wrapped up seven years behind schedule in 2023 and 2024 and cost more than twice as much as expected—about $35 billion for the pair. Along the way, Westinghouse, based in Cranberry Township, Penn., filed for Chapter 11 bankruptcy protection.

Chief executives of investor-owned utilities know that if they were to propose committing to similar projects on the same commercial terms, they’d be sacked on the spot. As a result, the private sector in the United States has been unwilling to take on the financial risk inherent in building new reactors.

The $80 billion deal with the federal government represents the U.S. nuclear industry’s best opportunity in a generation for a large-scale construction program. But ambition doesn’t guarantee successful execution. The delays and cost overruns that dogged the Vogtle project present real threats for the next wave of reactors.

Streamlining AP1000 Reactor Construction

What might be different about the next set of AP1000s? On the positive side, delivering multiple copies of the same reactor ought to create the conditions for a steady decline in costs. Vogtle Unit 3 was the first AP1000 to be built in the United States, and the lessons learned from it resulted in Vogtle Unit 4 costing 30 percent less than Unit 3. (Six AP1000s are currently operating outside the United States, and 14 more are under construction, according to Westinghouse.)

There’s been a bipartisan effort in the United States to streamline regulatory procedures to ensure that future projects won’t be delayed by the same issues that hampered Vogtle. The Accelerating Deployment of Versatile, Advanced Nuclear for Clean Energy (ADVANCE) Act that was signed into law by former U.S. President Joe Biden in 2024, includes several measures intended to improve processes at the Nuclear Regulatory Commission (NRC).

The last nuclear reactors to be built in the United States—Vogtle Units 3 and 4 in Waynesboro, Georgia—were completed seven years behind schedule and cost more than twice as much as expected. Georgia Power Co.

That included a mandated change in the NRC’s mission statement, setting a goal of “enabling the safe and secure use and deployment of civilian nuclear energy technologies”. It was a symbol of Congress’s intent to encourage the commission to support nuclear development.

In May President Trump built on that legislation with four executive orders intended to speed up reactor licensing and accelerate nuclear development—a framework that has yet to be tested in practice. In November the NRC published regulations setting out how it planned to implement the president’s orders. The changes are focused on removing redundant and duplicative rules.

... continue reading