Oracle stocks dipped about 5% on Wednesday following a report that discussions with Blue Owl Capital on backing a $10 billion data center in Michigan had stalled, although the cloud company later disputed the report.
Blue Owl had been in talks with Oracle about funding a 1-gigawatt facility for OpenAI in Saline Township, Michigan, according to the Financial Times.
However, the plans fell through due to concerns about Oracle's rising debt levels and extensive artificial intelligence spending, the FT reported, citing people familiar with the matter.
This comes as some investors raise red flags about the funding behind the rush to build ever more data centers.
The concern is that some hyperscalers are turning to private equity markets rather than funding the buildings themselves, and entering into lease agreements that could prove risky.
Blue Owl did look into the project, but pulled out due to unfavorable debt terms and the structure of repayments, according to a person familiar with the company's plans who asked not to be named in order to discuss a confidential matter.
Blue Owl is still involved in two other Oracle sites, the person said.
The person added that Blue Owl was also concerned that local politics in Michigan would cause construction delays.
Oracle later responded to the FT report, saying the project was moving forward and that Blue Owl was not part of equity talks.
"Our development partner, Related Digital, selected the best equity partner from a competitive group of options, which in this instance was not Blue Owl. Final negotiations for their equity deal are moving forward on schedule and according to plan," Oracle spokesperson Michael Egbert said in a statement.
... continue reading