The power line that could reshape New York’s grid is hitting snags

read original more articles
Why This Matters

The underground CHPE power line represents a significant step toward modernizing New York's energy infrastructure by increasing reliance on renewable hydropower from Quebec. Despite recent delays, its successful integration could substantially reduce emissions and enhance grid resilience, marking a pivotal move toward cleaner energy. Overcoming logistical and environmental challenges will be crucial for maximizing its impact on the region's sustainability goals.

Key Takeaways

An underground power line might not sound all that exciting, but this could be a big deal for the state’s grid planning, and for emissions. It could provide up to 20% of New York City’s electricity demand, largely with abundant hydropower from Quebec.

One wrinkle: The line has been down for most of this month, and some experts are concerned about how drought will affect the power supply feeding it. Let’s look at how the CHPE transmission line could help shape the future of our grid, and what barriers it needs to overcome to make a difference.

Planning for the CHPE (which is charmingly pronounced “chippy”) started 15 years ago, with the permitting process formally beginning in March 2010. The vision was to build infrastructure to better connect Quebec and southern New York.

Over 99% of Quebec’s electricity comes from renewable sources; most demand is met with hydropower, though the province’s wind capacity is growing quickly. New York has some hydropower of its own, as well as nuclear and wind, but the state still relies on fossil fuels for most of its energy generation.

Transmission Developers, a company owned by the alternative asset management firm Blackstone, and Hydro-Québec, the province’s manager of generation and transmission, partnered to build CHPE. Construction began in late 2022 and wrapped up earlier this year. The total cost for the privately funded project turned out to be $6 billion.

The construction of this line was a feat. It’s made up of a bundle of two high-voltage direct-current power cables, each measuring roughly five inches across. Developers buried the bundle underground or underwater across the length of New York State. Much of the line was laid at the bottom of the Hudson River, requiring special boats that shot water jets deep into the sediment to create trenches for the cable.

Connecting grids together can help accelerate the transition away from fossil fuels. The ability to move electricity to where it’s needed could also help limit the amount of new capacity we need to build. Research has shown that interconnection can help cut emissions and lower system costs.

But CHPE is off to a slow start and has seen two outages so far. The first, on July 1, was reportedly caused by a trip at a converter on the Canadian side of the border. The second outage began on July 4, and the power line is still down as of the morning of July 22.