Fervo Energy begins selling power from first enhanced geothermal plant at Cape Station

Fervo Energy said it started delivering electricity to the grid from its Cape Station facility on September 30, a day ahead of schedule, after the plant synchronized with the grid about a week earlier. The initial phase represents one-third of a planned 100-megawatt facility that took 23 months to build from groundbreaking to operation, with the full site potentially scaling to 4 gigawatts.

Google signs deal for 396 MW of Fervo geothermal power for Utah data center

Google has agreed to purchase nearly 400 megawatts of electricity from Fervo Energy's Cape Station geothermal plant in Utah, set to come online in 2028, with an option to buy 600 megawatts more through 2030. The power will support a new Google data center as the company seeks additional electricity sources to meet rising AI computing demands.